fbpx
Customize Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

Case Studies

Window Replacement Project


86-unit Co-op in the West Village

Initial Total Project Cost: $2.5 million
PMG Savings: 11% through negotiations of unit costs for interior restoration and re-negotiation of the change orders (COs)

Local Law 11 Project


116 unit Co-op in Lenox Hill

Total Project Cost: $743,000
PMG Savings: 25% by monitoring the scope closely, reviewing conditions called for in the scope, seeking alternative repair methods, and holding the GC / engineer accountable (credits, CO re-negotiations)

Façade Project


31-unit co-op in Park Slope

Total Project Cost: $300,000
PMG Savings: 13% through negotiations of unit costs for exterior restoration and re-negotiation of the change orders.

Local Law 11 Project


111-unit Co-op in Midtown East

Total Project Cost: $961,000
PMG Savings: 5% through negotiations of unit costs for exterior restoration, CO re-negotiations, and by holding the GC / Engineer accountable for days lost, oversight, delays etc.

ACM Removal Scope


172-unit Co-op in the East Village

Initial Proposals: $250,000
PMG Savings: PMG managed to negotiate and complete the scope with nearly 50% savings.

Energy Plant Upgrade


172-unit Co-op in the East Village

Total Project Cost: $9.6 million
PMG Savings: ~20% incentive, nearly $1.2 million from the City, and a 1% credit back for reimbursable expenses. Work involved a new chiller / HVAC and switching from a fancoil system to a heat pump system. AKAM procured funds from NYSERDA to pay for it.

Amenity Renovation (Gym / Locker Room / Pool)


1300-unit Co-op in the Riverdale, NY

PMG Savings: By phasing the work differently, PMG provided residents with a more enjoyable pool season by avoiding construction near the pool area. Additionally, PMG eliminated the need for extra construction fencing, saving the building $120,000.

Paving Project


148-unit Co-op on the Upper East Side

PMG Savings: PMG negotiated a $5,000 discount on a paver installation quote for the building.